Substation Scout

Gilbert Storage 34.5 kV

PJM queue ID AE1-244 Terminal status

Queue IDAE1-244
Project nameGilbert Storage 34.5 kV
Status (as published)Withdrawn
SubstationGilbert Storage
Point of interconnectionGilbert Storage 34.5 kV
CountyAtlantic
StateNJ
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2020-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity0
Mfo19.8
Withdrawn Date12/19/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.