Nottingham 230kV Reactor Bypass

PJM queue ID AE1-234 Terminal status

Queue IDAE1-234
Project nameNottingham 230kV Reactor Bypass
Status (as published)Withdrawn
SubstationNottingham Reactor Bypass
Point of interconnectionNottingham 230kV Reactor Bypass
CountyChester
StatePA
Voltage230 kV
Capacity578 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeUpgrade Request
Mfo578
Withdrawn Date10/2/2018