Substation Scout

Sunbury Solar

PJM queue ID AE1-225 Terminal status

Queue IDAE1-225
Project nameSunbury Solar
Status (as published)Withdrawn
SubstationColumbia-Sunbury
Point of interconnectionColumbia-Sunbury 69 kV
CountySnyder
StatePA
Voltage69 kV
Capacity9.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity9.4
Mfo19.8
Withdrawn Date6/24/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.