Substation Scout

Coleen-Clifford 138 kV

PJM queue ID AE1-220 Terminal status

Queue IDAE1-220
Project nameColeen-Clifford 138 kV
Status (as published)Withdrawn
SubstationColeen-Clifford
Point of interconnectionColeen-Clifford 138 kV
CountyNelson
StateVA
Voltage138 kV
Capacity66.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity66.7
Mfo100
Withdrawn Date6/17/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.