Coleen-Clifford 138 kV

PJM queue ID AE1-220 Terminal status

Queue IDAE1-220
Project nameColeen-Clifford 138 kV
Status (as published)Withdrawn
SubstationColeen-Clifford
Point of interconnectionColeen-Clifford 138 kV
CountyNelson
StateVA
Voltage138 kV
Capacity66.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity66.7
Mfo100
Withdrawn Date6/17/2019