PJM queue ID AE1-145 Terminal status

Queue IDAE1-145
Project nameWallops Island 69 kV
Status (as published)Withdrawn
SubstationWallops Island
Point of interconnectionWallops Island 69 kV
CountyAccomack
StateVA
Voltage69 kV
Capacity20 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2020-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date4/20/2022