McConnellsburg 138 kV

PJM queue ID AE1-132 Terminal status

Queue IDAE1-132
Project nameMcConnellsburg 138 kV
Status (as published)Withdrawn
SubstationMcConnellsburg
Point of interconnectionMcConnellsburg 138 kV
CountyFulton
StatePA
Voltage138 kV
Capacity51 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy85
Mw Capacity51
Mfo85
Withdrawn Date2/23/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.