Bethany 138 kV
PJM queue ID AE1-117 Terminal status
| Queue ID | AE1-117 |
|---|---|
| Project name | Bethany 138 kV |
| Status (as published) | Withdrawn |
| Substation | Bethany |
| Point of interconnection | Bethany 138 kV |
| County | Sussex |
| State | DE |
| Voltage | 138 kV |
| Capacity | 41.5 MW |
| Resource (as published) | Offshore Wind |
| Resource category | Offshore Wind (normalised for filtering) |
| Target commercial operation | 2022-06-01 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 152 |
| Mw Capacity | 41.5 |
| Mfo | 152 |
| Withdrawn Date | 7/15/2022 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.