Substation Scout

Five Points-Pantego 115 kV

PJM queue ID AE1-088 Terminal status

Queue IDAE1-088
Project nameFive Points-Pantego 115 kV
Status (as published)Withdrawn
SubstationFive Points-Pantego
Point of interconnectionFive Points-Pantego 115 kV
CountyBeaufort
StateNC
Voltage115 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date4/17/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.