Substation Scout

Round Hill Solar

PJM queue ID AE1-084 Terminal status

Queue IDAE1-084
Project nameRound Hill Solar
Status (as published)Withdrawn
SubstationBarterbrook-Stuarts Draft
Point of interconnectionBarterbrook-Stuarts Draft 115 kV
CountyAugusta
StateVA
Voltage115 kV
Capacity49.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy83
Mw Capacity49.8
Mfo83
Withdrawn Date7/11/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.