Substation Scout

Wylie Ridge 500 kV

PJM queue ID AE1-080 Terminal status

Queue IDAE1-080
Project nameWylie Ridge 500 kV
Status (as published)Withdrawn
SubstationWylie Ridge
Point of interconnectionWylie Ridge 500 kV
CountyWashington
StatePA
Voltage500 kV
Capacity80 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2022-02-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity80
Mfo1075
Withdrawn Date3/26/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.