Elwood 345 kV

PJM queue ID AE1-070 Terminal status

Queue IDAE1-070
Project nameElwood 345 kV
Status (as published)Withdrawn
SubstationElwood
Point of interconnectionElwood 345 kV
CountyWill
StateIL
Voltage345 kV
Capacity135 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2020-12-31
Source datasetcycle

Additional filed fields

DeveloperElwood Energy, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy0.0
Mw Capacity135.0
Mfo1610.0
Submitted Date7/31/2018
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/27/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.