Morrisville 230 kV

PJM queue ID AE1-022 Terminal status

Queue IDAE1-022
Project nameMorrisville 230 kV
Status (as published)Withdrawn
SubstationMorrisville
Point of interconnectionMorrisville 230 kV
CountyFauquier
StateVA
Voltage230 kV
Capacity111.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-11-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity111.7933
Mfo200
Withdrawn Date6/21/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.