Pulaski Community Solar

PJM queue ID AE1-018 Terminal status

Queue IDAE1-018
Project namePulaski Community Solar
Status (as published)Withdrawn
SubstationPeak Creek-Memoria Drive
Point of interconnectionPeak Creek-Memoria Drive 12 kV
CountyPulaski
StateVA
Voltage12 kV
Capacity2.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity2.8
Mfo5
Withdrawn Date2/21/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.