Substation Scout

Trowbridge-Pantero 115 kV

PJM queue ID AD2-195 Terminal status

Queue IDAD2-195
Project nameTrowbridge-Pantero 115 kV
Status (as published)Withdrawn
SubstationTrowbridge-Pantero
Point of interconnectionTrowbridge-Pantero 115 kV
CountyWashington
StateNC
Voltage115 kV
Capacity55.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity55.9
Mfo80
Withdrawn Date9/25/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.