Trowbridge-Pantero 115 kV

PJM queue ID AD2-195 Terminal status

Queue IDAD2-195
Project nameTrowbridge-Pantero 115 kV
Status (as published)Withdrawn
SubstationTrowbridge-Pantero
Point of interconnectionTrowbridge-Pantero 115 kV
CountyWashington
StateNC
Voltage115 kV
Capacity55.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity55.9
Mfo80
Withdrawn Date9/25/2018