Substation Scout

Scioto Farms Solar Project

PJM queue ID AD2-162 Terminal status

Queue IDAD2-162
Project nameScioto Farms Solar Project
Status (as published)Withdrawn
SubstationBiers Run-Circleville
Point of interconnectionBiers Run-Circleville 138kV
CountyPickaway
StateOH
Voltage138 kV
Capacity73.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy110
Mw Capacity73.81
Mfo110
Withdrawn Date6/21/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.