Chestnut 345kV
PJM queue ID AD2-159 Terminal status
| Queue ID | AD2-159 |
|---|---|
| Project name | Chestnut 345kV |
| Status (as published) | Withdrawn |
| Substation | Chestnut |
| Point of interconnection | Chestnut 345kV |
| County | Macon |
| State | IL |
| Voltage | 345 kV |
| Capacity | 33 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | Not reported |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 187.5 |
| Mw Capacity | 33 |
| Mfo | 187.5 |
| Withdrawn Date | 3/4/2022 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.