Newport News Battery Storage

PJM queue ID AD2-049 Terminal status

Queue IDAD2-049
Project nameNewport News Battery Storage
Status (as published)Withdrawn
SubstationNewport News
Point of interconnectionNewport News 23kV
CountyCity of Newport News
StateVA
Voltage23 kV
Capacity10 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-04-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity10
Mfo10
Withdrawn Date10/21/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.