Substation Scout

Crystal Hill 115 kV

PJM queue ID AD2-043 Terminal status

Queue IDAD2-043
Project nameCrystal Hill 115 kV
Status (as published)Withdrawn
SubstationCrystal Hill
Point of interconnectionCrystal Hill 115 kV
CountyHalifax
StateVA
Voltage115 kV
Capacity30 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-01-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy65.5
Mw Capacity30
Mfo65.5
Withdrawn Date12/20/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.