Jacksonville-Renaker 138kV IV

PJM queue ID AD2-036 Terminal status

Queue IDAD2-036
Project nameJacksonville-Renaker 138kV IV
Status (as published)Withdrawn
SubstationJacksonville-Renaker IV
Point of interconnectionJacksonville-Renaker 138kV IV
CountyHarrison
StateKY
Voltage138 kV
Capacity40 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity40
Mfo60
Withdrawn Date8/19/2019