Pamplin Solar

PJM queue ID AD1-160 Terminal status

Queue IDAD1-160
Project namePamplin Solar
Status (as published)Withdrawn
SubstationPamplin
Point of interconnectionPamplin 34.5 kV
CountyAppomattox
StateVA
Voltage34.5 kV
Capacity6.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15.7
Mw Capacity6.6
Mfo15.7
Withdrawn Date1/14/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.