Substation Scout

Martinsville-Wilmington 69 kV

PJM queue ID AD1-147 Terminal status

Queue IDAD1-147
Project nameMartinsville-Wilmington 69 kV
Status (as published)Withdrawn
SubstationMartinsville-Wilmington
Point of interconnectionMartinsville-Wilmington 69 kV
CountyClinton
StateOH
Voltage69 kV
Capacity30 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity30
Mfo50
Withdrawn Date10/3/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.