Substation Scout

Muskingum River 345 kV Phase II

PJM queue ID AD1-091 Terminal status

Queue IDAD1-091
Project nameMuskingum River 345 kV Phase II
Status (as published)Withdrawn
SubstationMuskingum River Phase II
Point of interconnectionMuskingum River 345 kV Phase II
CountyWashington
StateOH
Voltage345 kV
Capacity590 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2022-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy630
Mw Capacity590
Mfo630
Withdrawn Date11/7/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.