Substation Scout

Cape Solar

PJM queue ID AD1-083 Terminal status

Queue IDAD1-083
Project nameCape Solar
Status (as published)Withdrawn
SubstationPage-Bethel
Point of interconnectionPage-Bethel 138 kV
CountyPage
StateVA
Voltage138 kV
Capacity60.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity60.1
Mfo100
Withdrawn Date7/21/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.