Substation Scout

Sporn South 138 kV

PJM queue ID AD1-051 Terminal status

Queue IDAD1-051
Project nameSporn South 138 kV
Status (as published)Withdrawn
SubstationSporn South
Point of interconnectionSporn South 138 kV
CountyMason
StateWV
Voltage138 kV
Capacity18.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy30
Mw Capacity18.4
Mfo30
Withdrawn Date6/4/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.