Culpeper 34.5 kV

PJM queue ID AD1-049 Terminal status

Queue IDAD1-049
Project nameCulpeper 34.5 kV
Status (as published)Withdrawn
SubstationCulpeper
Point of interconnectionCulpeper 34.5 kV
CountyCulpeper
StateVA
Voltage34.5 kV
Capacity6.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity6.3
Mfo20
Withdrawn Date9/11/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.