Substation Scout

Darby-East Liberty 69 kV

PJM queue ID AD1-035 Terminal status

Queue IDAD1-035
Project nameDarby-East Liberty 69 kV
Status (as published)Withdrawn
SubstationDarby-East Liberty
Point of interconnectionDarby-East Liberty 69 kV
CountyUnion
StateOH
Voltage69 kV
Capacity19 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity19
Mfo50
Withdrawn Date2/20/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.