Substation Scout

North Bergen I 480V

PJM queue ID AD1-002 Terminal status

Queue IDAD1-002
Project nameNorth Bergen I 480V
Status (as published)Withdrawn
SubstationNorth Bergen I 480 v
Point of interconnectionNorth Bergen I 480 v
CountyHudson
StateNJ
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2020-01-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0.21
Mw Capacity0
Mfo0.21
Withdrawn Date6/6/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.