Substation Scout

Sussex-Harbeson 69kV

PJM queue ID AC2-190 Terminal status

Queue IDAC2-190
Project nameSussex-Harbeson 69kV
Status (as published)Withdrawn
SubstationSussex-Harbeson
Point of interconnectionSussex-Harbeson 69kV
CountySussex
StateDE
Voltage69 kV
Capacity9.6 MW
Resource (as published)Methane
Resource categoryGas (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy9.6
Mw Capacity9.6
Mfo9.6
Withdrawn Date9/15/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.