Substation Scout

Crisfield-Kings Creek 69kV

PJM queue ID AC2-189 Terminal status

Queue IDAC2-189
Project nameCrisfield-Kings Creek 69kV
Status (as published)Withdrawn
SubstationCrisfield-Kings Creek
Point of interconnectionCrisfield-Kings Creek 69kV
CountySomerset
StateMD
Voltage69 kV
Capacity10.3 MW
Resource (as published)Methane; Solar
Resource categoryHybrid (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy11.6
Mw Capacity10.3
Mfo11.6
Withdrawn Date4/17/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.