Double Tollgate Solar Project
PJM queue ID AC2-174 Terminal status
| Queue ID | AC2-174 |
|---|---|
| Project name | Double Tollgate Solar Project |
| Status (as published) | Withdrawn |
| Substation | Double Tollgate |
| Point of interconnection | Double Tollgate 34.5kV |
| County | Clarke |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 3.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2023-03-31 |
| Source dataset | serial |
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 10 |
| Mw Capacity | 3.8 |
| Mfo | 10 |
| Withdrawn Date | 2/28/2024 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.