Substation Scout

Jeffersonville 69kV

PJM queue ID AC2-171 Terminal status

Queue IDAC2-171
Project nameJeffersonville 69kV
Status (as published)Withdrawn
SubstationJeffersonville
Point of interconnectionJeffersonville 69kV
CountyRoss
StateOH
Voltage69 kV
Capacity11 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy29
Mw Capacity11
Mfo29
Withdrawn Date8/23/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.