Waterman 34 kV

PJM queue ID AC2-166 Terminal status

Queue IDAC2-166
Project nameWaterman 34 kV
Status (as published)Withdrawn
SubstationWaterman
Point of interconnectionWaterman 34 kV
CountyDeKalb
StateIL
Voltage34 kV
Capacity19 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-12-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy40
Mw Capacity19
Mfo40
Withdrawn Date9/25/2018