Substation Scout

Sweetspire

PJM queue ID AC2-162 Terminal status

Queue IDAC2-162
Project nameSweetspire
Status (as published)Withdrawn
SubstationOld Church
Point of interconnectionOld Church 34.5kV
CountyHanover
StateVA
Voltage34.5 kV
Capacity13.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity13.2
Mfo20
Withdrawn Date9/10/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.