Substation Scout

Jackson-Woodland 115kV

PJM queue ID AC2-159 Terminal status

Queue IDAC2-159
Project nameJackson-Woodland 115kV
Status (as published)Withdrawn
SubstationJackson-Woodland
Point of interconnectionJackson-Woodland 115kV
CountyNorthhampton
StateNC
Voltage115 kV
Capacity40 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity40
Mfo80
Withdrawn Date11/2/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.