Gunn Road 345kV

PJM queue ID AC2-124 Terminal status

Queue IDAC2-124
Project nameGunn Road 345kV
Status (as published)Withdrawn
SubstationGunn Road
Point of interconnectionGunn Road 345kV
CountyHardin
StateOH
Voltage345 kV
Capacity19 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-12-15
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity19
Mfo50
Withdrawn Date11/19/2018