Lick Run 115kV

PJM queue ID AC2-122 Terminal status

Queue IDAC2-122
Project nameLick Run 115kV
Status (as published)Withdrawn
SubstationLick Run
Point of interconnectionLick Run 115kV
CountySomerset
StatePA
Voltage115 kV
Capacity19 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity19
Mfo50
Withdrawn Date12/10/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.