Substation Scout

Marysville-Sorenson 765kv

PJM queue ID AC2-104 Terminal status

Queue IDAC2-104
Project nameMarysville-Sorenson 765kv
Status (as published)Withdrawn
SubstationMarysville-Sorenson
Point of interconnectionMarysville-Sorenson 765kv
CountyVan Wert
StateOH
Voltage765 kV
Capacity65 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy500.25
Mw Capacity65.03
Mfo500.25
Withdrawn Date11/7/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.