Shugart Solar

PJM queue ID AC2-101 Terminal status

Queue IDAC2-101
Project nameShugart Solar
Status (as published)Withdrawn
SubstationRipley-Nanjemoy
Point of interconnectionRipley-Nanjemoy 69kV
CountyCharles
StateMD
Voltage69 kV
Capacity12.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-03-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy32.5
Mw Capacity12.35
Mfo32.5
Withdrawn Date12/3/2020