Substation Scout

Buckhorn-Lonesome Pine 138kV

PJM queue ID AC2-098 Terminal status

Queue IDAC2-098
Project nameBuckhorn-Lonesome Pine 138kV
Status (as published)Withdrawn
SubstationBuckhorn-Lonesome Pine
Point of interconnectionBuckhorn-Lonesome Pine 138kV
CountyTazewell
StateVA
Voltage138 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity60
Mfo100
Withdrawn Date8/30/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.