Substation Scout

Brunswick-Wake 500 kV

PJM queue ID AC2-093 Terminal status

Queue IDAC2-093
Project nameBrunswick-Wake 500 kV
Status (as published)Withdrawn
SubstationBrunswick-Wake
Point of interconnectionBrunswick-Wake 500 kV
CountyNorthhampton
StateNC
Voltage500 kV
Capacity429.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy675
Mw Capacity429.4
Mfo675
Withdrawn Date7/6/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.