Substation Scout

Kiski Valley

PJM queue ID AC2-076 Terminal status

Queue IDAC2-076
Project nameKiski Valley
Status (as published)Withdrawn
SubstationKiski Valley–Vandergrift
Point of interconnectionKiski Valley–Vandergrift 25 kV
CountyWestmoreland
StatePA
Voltage25 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2020-04-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity19.9
Mfo19.9
Withdrawn Date10/22/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.