Substation Scout

EAst Beaver 138kV

PJM queue ID AC2-046 Terminal status

Queue IDAC2-046
Project nameEAst Beaver 138kV
Status (as published)Withdrawn
SubstationEAst Beaver
Point of interconnectionEAst Beaver 138kV
CountyJackson
StateOH
Voltage138 kV
Capacity39.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy63
Mw Capacity39.3
Mfo63
Withdrawn Date9/26/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.