Hillsboro 138kV

PJM queue ID AC2-042 Terminal status

Queue IDAC2-042
Project nameHillsboro 138kV
Status (as published)Withdrawn
SubstationHillsboro
Point of interconnectionHillsboro 138kV
CountyHighland
StateOH
Voltage138 kV
Capacity120 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity120
Mfo200
Withdrawn Date10/18/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.