Greenfield-Buckskin 69kV

PJM queue ID AC2-020 Terminal status

Queue IDAC2-020
Project nameGreenfield-Buckskin 69kV
Status (as published)Withdrawn
SubstationGreenfield-Buckskin
Point of interconnectionGreenfield-Buckskin 69kV
CountyRoss
StateOH
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date8/3/2018