Substation Scout

Wildcat 12kV

PJM queue ID AC2-008 Terminal status

Queue IDAC2-008
Project nameWildcat 12kV
Status (as published)Withdrawn
SubstationWildcat
Point of interconnectionWildcat 12kV
CountyHighland
StateOH
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2019-06-03
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity0
Mfo10
Withdrawn Date6/5/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.