Chase-City-Twittys Creek 115kV
PJM queue ID AC1-215 Terminal status
| Queue ID | AC1-215 |
|---|---|
| Project name | Chase-City-Twittys Creek 115kV |
| Status (as published) | Withdrawn |
| Substation | Chase-City-Twittys Creek |
| Point of interconnection | Chase-City-Twittys Creek 115kV |
| County | Mecklenburg |
| State | VA |
| Voltage | 115 kV |
| Capacity | 68.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2018-06-30 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 100 |
| Mw Capacity | 68.8 |
| Mfo | 100 |
| Withdrawn Date | 6/21/2017 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.