Substation Scout

Kings Creek 25kV

PJM queue ID AC1-180 Terminal status

Queue IDAC1-180
Project nameKings Creek 25kV
Status (as published)Withdrawn
SubstationKings Creek
Point of interconnectionKings Creek 25kV
CountySomerset
StateMD
Voltage25 kV
Capacity6 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2019-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6
Mw Capacity6
Mfo6
Withdrawn Date3/20/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.