Kings Creek 25kV

PJM queue ID AC1-177 Terminal status

Queue IDAC1-177
Project nameKings Creek 25kV
Status (as published)Withdrawn
SubstationKings Creek
Point of interconnectionKings Creek 25kV
CountyQueen Anne's
StateMD
Voltage25 kV
Capacity4 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2019-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy4
Mw Capacity4
Mfo4
Withdrawn Date5/28/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.