PJM queue ID AC1-143 Terminal status

Queue IDAC1-143
Project nameElkwood Solar
Status (as published)Withdrawn
SubstationBrandy-Remington
Point of interconnectionBrandy-Remington 115kV
CountyCulpeper
StateVA
Voltage115 kV
Capacity41.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-16
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity41.2
Mfo60
Withdrawn Date1/12/2026