Substation Scout

Leatherwood

PJM queue ID AC1-117 Terminal status

Queue IDAC1-117
Project nameLeatherwood
Status (as published)Withdrawn
SubstationStockton
Point of interconnectionStockton 34.5kV
CountyHenry
StateVA
Voltage34.5 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date2/19/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.